I see a large number of new housing constructed and in the process of being constructed, in Whitfield.
- Can you inform me how many of the new housing in Whitfield currently lies empty and why?
- Who will be occupying all the many more housing that is planned for Whitfield?
- Why are so many houses being built in Whitfield and how many will be social housing or for first time buyers?
- Has any of the sites in Whitfield been bought by external investors?
Response
1. Occupations data received via Council Tax reports that 543 properties are currently occupied/paying Council Tax August 2026 against our completion figure of 818 completions. (Our completion figure is monitored at a certain level of building works completions ie. Roof/Walls completed rather than the property ready to move into). The Council does not hold data of why some properties are empty/remain to be sold, this information will be available from the developers.
2. The Council does not hold this information.
3. The Whitfield Urban Expansion (WUE) was originally allocated in the Core Strategy 2010 and has been re-allocated for a total of 6,350 homes in the Local Plan 2024. Two outline planning permissions were granted under Phase 1 and 1A, totalling 1,350 units, comprising:
- 10/01011: 100 homes in Phase 1A - a new community hub/District centre and other required infrastructure, the homes were built by 2023.
- 10/01010: 1,250 homes in Phase 1 - Outline consent
- There is consent for 1,023 of these units through Reserved Matters (RM) applications
- There are 338 extant units on these RM applications still to be completed
- There remains 327 units without full consent on the 10/01010 application
- 21/00075: 38 homes in Phase 1 – Outline consent has been granted consent
- During 2025-26, 114 new homes have been built across various planning applications in Phase 1
In addition, Phase 4 of WUE at Singledge Lane for 133 homes was completed in 2023.
The total number of houses built across the whole WUE development as of March 2026 is 818, and a further 703 have consent.
Applications awaiting consent
Two applications for Phase 2 have been submitted and are awaiting a resolution to grant:
- 23/00830: 300 homes in Phase 2 – Outline application
- 23/01458: 430 homes in Phase 2 – Hybrid application including the provision of two community football pitches
With regards to affordable housing units:
- Phase 1 includes 4 Affordable Housing units, secured by a DoV (Deed of Variation) to the S106 for application 10/01010, dated 3rd November 2025.
- Part of Phase 1A was transferred to the council and has been used to deliver 26 Affordable Housing under RM (Reserved Matters) approval 17/00056.
- Application 21/00075 includes 25% to be delivered as Affordable housing type 'first homes'
- Affordable housing will also be required as part of the two Phase 2 applications detailed above in accordance with the Council's policy.
4. The Council does not hold this information.